Tag Archives: Works and Projects

On the 5th of January, 2014, B.CLIP students went on a site visit to the CNR Rao circle underpass near IISc. Mr. B N Vishwanath, an independent auditor at the JNNURM, walked the students through how an infrastructure project is conceptualized, and why they often fail or get delayed.

Field Trip Part 1: CNR Rao Circle Underpass

On January 5, B.CLIP students went on a site visit to the CNR Rao underpass near IISc. Mr. B N Vishwanath, an independent auditor at the JNNURM, walked the students through how infrastructure projects are conceptualised, and why they often fail or get delayed.

This project sits on an arterial path in Bangalore, and it was planned with the aim to ease vehicular congestion and facilitate easy movement of traffic between Mekhri circle, Malleshwaram and Yeshwantpur. The underpass leads on one side to National Highway 4 which links 20 districts of Karnataka.

This is a project taken up under the national Jawaharlal Nehru National Urban Renewal Mission (JNNURM) scheme and was sanctioned as a turnkey project in early 2008 at the cost of about 30 crores. Stipulated to be completed in 10 months, it is now fast approaching 60 months since project start. With many months and years of inactivity, there is breakneck progress in the work over the past three months and the underpass is set for full use in the next few weeks.